IHIF Commercial, LLC
IHIF Commercial, LLC has begun construction activities on the lots adjacent to 6th Ave NE. This work includes the site development work for new town home buildings. Construction will occur in phases over the coming months and will include:
- Site Preparation and Grading
- Utility Installation
- Retaining Walls and Infrastructure Improvements
- Paving

Construction Updates:
FALL 2025 TO FALL 2026
IHIF Commercial, LLC has begun construction of a new park located on the southwest side of our property adjacent to NE Discovery Drive and the West Highlands Park neighborhood. This will be an active work area over the coming months as we complete grading, utilities, and site features for the future park space. Please check this site for any updates or traffic control measures.
Please be advised that parking spaces #22–28 on 5th Place NE will be temporarily closed during June 15th – June 18th for construction activities. We will install no-parking signs, cones, and temporary fencing during construction hours (7 AM – 4:30 PM). Please relocate vehicles prior to the start of work.
Upcoming road closure for paving Mon. June 8 – Wed. June 10

Upcoming road closure for utility tie in Tues. June 16 – Thurs. June 18

As of January 19th Sidewalk & parking will be closed immediately adjacent to Lot 9 for pedestrian safety and equipment access.
- Closure will be in effect for the duration of the Project – re-opening July 2026
NOVEMBER 2025
Completion of Discovery Road right of way road work. All traffic control removed.
SPRING/SUMMER/FALL 2025
IHIF Commercial, LLC has finished their work on NE Discovery Drive. All traffic control has been removed. Please continue to check this page for any upcoming traffic impacts.
MARCH 2025
IHIF Commercial, LLC will break ground on our IHIF Commercial project this month. You will see construction progress of:
- Survey for underground work
- Mobilize equipment and material to project site
- Set up traffic control
- Establish work limits and install erosion control components
FEBRUARY 2025
Duration of First Phase of Discovery Drive Right of Way Work and Site Preparation for Issaquah High Street Collection Project is scheduled to start Spring 2025 and run through Fall of 2025. Please check back here for road and infrastructure improvements.
Community Update
Please note that Excel Pacific has started work on the corner lot – 9th Ave NE and NE Discovery Drive (Lot 6). Work will be progressing on this lot, with staging planned on the adjacent lot (Lot 5). Please see the marked image below for reference.

If you have any questions or concerns regarding these lots, potential road closures, or related construction impacts, please direct them to the contact below as these lots are not under IHIF Commercial’s ownership.
John Hughes